Major rail track renewal between Clontarf Road and KIllester Stations
Cllr. Heney wishes to inform constituents that Iarnród Éireann will be carrying out major track renewal works between Clontarf Road and KIllester Stations as follows;
Main Works
Sat night/Sun morning 16th July
Mon night/Tues morning 18th to Sat night/Sun morning 23rd July
Mon night/Tues morning 25th to Sat night/Sun morning 30th July
Mon night/Tues morning 1st to Fri night/Sat morning 5th August
Tues night/Wed morning 9th to Sat night/Sun morning 13th August
Mon night/Tues morning 15th to Sat night/Sun morning 20th August
Follow on Works
Mon night/Tues morning 22nd to Sat night/Sun morning 27th August
The work necessitates the replacement of rails, sleepers and ballast and requires the use of heavy duty on-track machines and cutting/grinding power tools. Work will start at 1am and be finished at 5am except on Sunday mornings when work will finish at 8am.
This work will involve the access/egress of on-track machines and the loading of materials/ballast in the Killester Compound area for the duration of the works